The Gunnison City Council heard a presentation on capacity, potential locations, cost and other design considerations for the city’s water treatment plant construction project at its Nov. 17 meeting.
Gunnison Public Works Director Pete Rice noted that the planning process for the water treatment plant has lasted five years and has been driven by the need to provide a more reliable, contamination-resistant water supply for the city and by the advantages of its very senior water rights.
He said that the city has pursued a progressive design-build construction delivery method, which has the key advantage of the city being able to analyze costs at all steps of the project, instead of only when the project is bid out for construction. The city’s process involves Haskell as the primary builder and contractor with Hazen and Sawyer providing engineering assistance.
Jeremy McVey, senior director of project development at the engineering and construction firm Haskell, noted the previous work the company had done on the project, including data analysis to determine the specific capacity needed for the project, altering the water treatment method compared to previous plans to make it less expensive and more practical, and various other activities.
Matt Ridens, associate engineer at Hazen and Sawyer, said that following analysis of previous data and growth projections, the engineers worked to "right-size" the project to ensure that it would last through the duration of the payments on the funding needed to support it.
He said they eventually settled on a water treatment capacity of 4 million gallons per day, which would provide the city with 15 to 20 years before any expansion would need to start, with the plant’s installed capacity designed to last up to 60 years.
McVey said that the engineers and city staff held a community stakeholder meeting and an open house in August to hear feedback on the plans for the plant, which he said was generally "very positive."
He then presented Haskell and Hazen and Sawyer’s 30% design and cost estimate, including renderings of the proposed building design and their estimate of the plant’s cost at $99,890,290, which he stated industry standards suggest could vary by 20% from the final cost when fully designed.
McVey said that, following a meeting with Rice in September, the team worked to find ways to reduce the cost, since the cost estimate was above what would be feasible for Gunnison and was above the $60 million plant cost anticipated by the city’s ongoing water rate study, which will guide the setting of user rates to fund the plant and other projects.
From recent work on cost reductions, he said the team believed it had identified $15 million to $30 million in potential savings for the project, bringing the project cost down to between $70 million and $78 million.
Ridens and McVey highlighted that this included changes to the water treatment system for the plant, deferring construction of additional groundwater wells to feed the plant, and altering the site for the plant.
Rice explained the engineers and city staff considered a variety of alternative sites for the plant, before settling on a staff recommendation of relocating the plant from its present proposed location on the western end of County Road 13 in Van Tuyl Ranch to the lower southeast corner of the ranch near the Gunnison Library and the Gunnison Community School.
He indicated that this alternative site would lower costs by reducing the distance between the plant and the river intake at the Gunnison River as well as blending into the environment and nearby buildings in the area.
“The cost is driving this, to be quite blunt,” Rice said, adding that this change would require significant additional public outreach.
Mayor Diego Plata suggested that the alternative location could enhance opportunities for schoolchildren to visit the plant and learn how their water is treated.
Ridens then covered the funding strategy for the plant. He said that the group had been working on a variety of funding approaches, including pursuing loans and grants from the U.S. Department of Agriculture, which Ridens said would be the best funding source available; federal Water Infrastructure Finance and Innovation Act loans or Colorado State Revolving Fund loans.
McVey said that the group plans to apply for funding to have city council approve a guaranteed maximum price for the project in mid-2027 and mobilize for construction in spring 2028 with completion of the plant construction in the summer of 2030. He added that the group also plans to continue public outreach in the future, including community stakeholder meetings and open houses.
Council member Audrey Zahradka asked if bringing the plant closer to homes by relocating it would cause noise issues.
McVey and Rice said that noise mitigation and impacts would have to be considered as part of the ongoing design. Gunnison City Manager Amanda Wilson added that issues related to the location change would have to be voted on by the council due to the planned unit development zoning that governs uses for the Van Tuyl Ranch.
Plata asked how the city would make the decision on where to locate the plant.
Wilson replied that the city would need to formulate a schedule and that staff wanted council feedback on issues the council would want to discuss further. However, the council would have to make decisions at the project's plant design milestones, at a minimum.
Plata said public input would be important and that he would want to discuss the plant location and funding sources further.
Council member Loren Ahonen asked what the cost impact of moving the plant from a 4 MGD to a 3 MGD treatment capacity would be.
Ridens explained that this decrease would lower costs by about $2.2 million, which McVey said was not considered to be a significant amount of cost savings for the impact on the plant’s capabilities.
Ahonen said he was a "strong advocate" for relocating the plant due to the cost savings.
Following further discussion of the location change, Rice said staff would bring back information about the site change for further council discussion in the future.
Plata said he would also like to have further discussion of the impacts of the project on the city ditch system, which Rice said could also be brought back for further discussion.
Council member Matt Schwartz said he would also like to discuss the process of expanding the plant further.
“Very helpful, very thorough review, and thank you to all the staff that helped provide this information,” said Plata.