Main utilities for Gunnison Rising near completion

Posted

Contractors used a special boring machine to place massive pipes that will hold utility lines underneath Hwy. 50 to prevent highway closures.

Although it’s difficult to see from Hwy. 50, construction crews are hard at work installing electrical, sewer and water lines large enough to support a development that will be one third the size of Gunnison. 

The freshly installed infrastructure, once it’s completed, will accommodate the first phase of the Gunnison Rising subdivision, a new development located just east of town. Gunnison Rising will be built out in multiple phases on more than 600 acres. 

Construction at the “government campus” — the project’s first phase on the south side of the highway — began last spring, along with the installation of main lines and infrastructure that future phases will be able to tie into in the future. The total cost of the infrastructure in progress has exceeded $10 million — an expense that is being covered by developers. 

The government campus contains a 38,000 square-foot FedEx distribution center, which will be ready for

move-in in the coming weeks. The Bureau of Land Management’s new field office, the second building taking shape on the site, will not be ready until the start of 2023. The infrastructure — roads, and sewer and water lines — that will accommodate not only those two buildings, but the rest of the development, are “on the track to completion,” said City Engineer Cody Tusing. 

As the construction site bustled with activity, Tusing said it’s like “SimCity, but just the real deal.” 

Gunnison Rising has had to overcome major utility hurdles over the past year, including expanding the city’s electrical and sewer capacity and routing the utilities to the site. Contractors used a special boring machine to place massive pipes that will hold utility lines underneath Hwy. 50 to prevent highway closures. While the water and sewer lines are expected to be in before the end of the month, the city staff is still in the process of expanding Gunnison’s northern substation. Permanent power from the city’s grid will likely not be available until 2023.   

A road template for the site is also beginning to form. The primary connection to the government campus will be “Ute Lane,” which is under construction, and “Hartman Avenue,” a road that will be slightly east of the entrance to I Bar Ranch. According to project manager Jeff Prosapio, once it is complete, it will become a new intersection with a roundabout. Construction will likely not begin until 2024, he said. 

Despite the challenges of creating a system that is prepared to handle future growth, that infrastructure will be “ready and waiting,” Tusing said. This is the first and likely largest infrastructure build-out, setting the pace for future phases. It will be followed by smaller segments of utility development throughout the subdivision. 

“That's a big appeal,” Tusing said. “We deal with a lot of developers around town, and one of the biggest hurdles to tackle is getting utilities to the site … The utilities will be there for Gunnison Rising and that will make the second phase go a lot faster.” 

Two other contracts are in motion for Gunnison Rising, including a gas station and an affordable housing development. Phase two, which encompasses approximately 50 acres to the north of Hwy. 50 near Western Colorado University, will include the development’s first residential construction. 

City leaders are hopeful that Gunnison Rising will boost the stock of affordable housing available for local workers. In May, the City of Gunnison received a $1.8 million grant from the Department of Local Affairs (DOLA) that will fund a 64-unit townhome development at Gunnison Rising. Infrastructure for the affordable housing project will start going in place next spring. 

“We're just particularly excited about that being in the first phase of housing, because we firmly believe that's going to set the culture and expectations of the development,” said Community Development Director Anton Sinkewich. 

Although the winter months will slow progress, Prosapio said he expects to have a robust spring. His team has begun discussions with local builders who have interest in targeting “middle-market or attainable housing” in what will become Gunnison Rising’s first neighborhoods on the north side of the highway. He hopes homes will begin to “go vertical” in 2023. 